Project Management: Finance Perspective
The success of any organisation depends on how well it can deliver its products & services to customer. However, before it can deliver its product which meets customer expectations, it needs to undertake certain projects to develop the products or services or innovate to meet the customer expectations. Some Organisation in fact are in the long-term infrastructure business where the business itself is a combination of individual projects which they need to deliver to their customer. Thus, Project Management is very crucial for any organization as the success of the delivered projects (internal or external) will ensure the success and growth of the organization.
Post-COVID, all the major governments have pushed for infrastructure spending which is important to boost & revive the economy from the impact of COVID-19. India too is not an exception and has started pushing for infrastructure projects. The same was also seen in Union Budget 2021, 2022 and 2023 where the government has allocated Rs. 5.54 Lacs Crore, Rs. 7.54 Lacs Crore and Rs. 10 Lacs Crore respectively (Note 1) as capital expenditure. Further as per Indian Infrastructure Sector in India Industry Report, India plans to spend US$ 1.4 trillion on infrastructure between 2019 to 2023.
With so much amount being spent on infrastructure projects, project management becomes very crucial to ensure the projects are completed not only on time but with the right quality and cost.
However, in our current & past projects, we have seen that there are lot of delays and cost overrun. Below is the data from Ministry of Statistics and Program Implementation, Government of India (MoSPI) for ~1,718 projects in India which shows only 17% of the projects are either on schedule or ahead of schedule. Further due to delays and other factors there is an anticipated cost overrun of INR 4.4 trillion (as per report in Aug 2021).
Running Late: MoSPI Infrastructure Project Monitoring (~1,718 Projects)
MoSPI monitors central infrastructure projects of ₹150 crore and above (Report: August 2021 | Image Source: Livemint Newspaper)
560 Projects
871 Projects
275 Projects
12 Projects
| Original Cost | Anticipated Completion Cost | Cost Overrun (19.9%) | Cumulative Expenditure (47.49%) | Cost Overrun Projects | Both Cost & Time Overrun |
|---|---|---|---|---|---|
| ₹ 22.0 Trillion | ₹ 26.4 Trillion | ₹ 4.4 Trillion | ₹ 12.5 Trillion | 470 | 214 |
The above data clearly shows that most of the projects are delayed and there is a cost overrun. In this case, it is very important to implement robust Project Management plans to ensure organization achieves the three critical goals of any project i.e. Cost, Time and Quality.
In this article, the major terms & process of Project Management is discussed.
Key Terms
A. What is Project Management?
Project Management can be defined as the process of leading the resources and using specific tools, knowledge, and techniques to achieve the project objectives. A Project can be of anything i.e. infrastructure projects (Construction of roads, buildings etc), development of new processes to improve the organization’s profitability, venturing into new businesses etc. Project Management focuses on:
- How to bring & take together the different cross-functional resources.
- Ensure that there is full coordination and corporation within them.
- It also involves handling the disputes between people.
- Making a trade-off between various projects objectives esp. Time, Cost & Quality.
“One of the distinguishing features of project management is that it has a finite timespan as all the projects have a start and endpoint. Any delay in the closure of the Project has a bigger repercussion in terms of an unsatisfied customer, additional cost, reduced quality etc. Thus, it becomes more crucial for the Project Managers to have a greater understanding of the various Project Management tools & techniques to successfully complete the projects.”
B. What is Project Team?
The Project Team includes the people from various cross-functional teams who join the projects and once it is completed move back to their functional team. The critical players in the project teams depend upon the type of projects, for e.g. in the case of infrastructure projects it will be:
There can be a few additional roles based on the requirement of the project.
C. What is Project Life Cycle?
1. What is Life Cycle: A Project life cycle covers the phases through which each project goes from start to completion. In general, there are 4 phases:
2. What are Gate Reviews: Gate Reviews in simple terms are checkpoints to ensure project progress is in line with objectives without surprises. It helps project managers track:
- Understand current status and readiness to move forward;
- Time, quality, and cost tracking;
- Identify variances against the plan and take corrective actions;
- Identify risks in the project and develop mitigation plans.
The number of gate reviews and timing are defined at the beginning of the project and cannot be changed without prior approval of senior management. Each review highlights bottlenecks and establishes reviewed action plans.
Sample Gate Reviews Flow:
Project Management: Key Processes from a Finance perspective
A. Project Reviews
Critical to have regular reviews with the cross-functional team to detect issues early and avoid surprises:
- 1. Weekly: Track open items, operational conflicts, and detailed line-by-line review of milestones.
- 2. Quarterly / Yearly: Broad status presented to Senior Management with intensive focus on the financial performance of the project.
B. Controlling & Monitoring
1. Work Breakdown Structure (WBS): Divide the entire project into a hierarchical WBS and assign KPIs (Quality, Cost, Time) and dedicated ownership to each element.
• WBS A2: Budget INR 20 Cr
• WBS B2: Budget ₹20 Cr
• WBS C2: Budget ₹10 Cr
2. Physical Progress vs Actual Cost Incurred: For long-term projects, tracking actual expenditure against physical progress is vital. Any variance indicates slippage or cost overrun:
- Planned Activities (Original Plan): 80% (Scheduled target)
- Actual Work Completion: 40% (40% delay slippage)
- Actual Cost Incurred: 45% (Additional 5% cost overrun over physical progress)
C. Risk Register
A Risk Register records risks and mitigation plans. Key components:
- 1. Identification: Defines risk and source of occurrence.
- 2. Quantification: Quantifies financial impact into: (a) Maximum / Risk Before Mitigation, and (b) Most Likely / Risk After Mitigation (residual risk + mitigation cost).
- 3. Classification: Categorized into technical, commercial, contractual, etc.
- 4. Mitigation Plan & Tracking: Actions, ownership, and tracking status.
- 5. Probability: Likelihood of occurrence; high probable risks demand immediate management action.
| S.No. | Particulars | Considered in Forecast | Probability | PIC | Closure Date | Mitigation Action | Max Potential | Most Likely |
|---|---|---|---|---|---|---|---|---|
| 1 | Increase in the Raw Material price | No | High | xx | Dec-21 | To negotiate with suppliers | 1000 | 100 |
| 2 | Delay in the project by xx months | No | Medium | xx | Feb-22 | Pull addl. resource to meet current timeline | XX | XX |
| 3 | Change of Design xx to xx | No | Low | xx | Feb-22 | XXXX | XX | XX |
D. Savings Register
Records all cost-saving opportunities to enhance project margins:
- 1. Identification: Defines ideas and application.
- 2. Quantification: Evaluates Maximum Potential and Most Likely savings.
- 3. Review Progress & Realization: Action items, PIC, and implementation tracking.
| S.No. | Particulars | PIC | Date | Action | Max Potential | Most Likely |
|---|---|---|---|---|---|---|
| 1 | Common validation with xx project | xx | Dec-21 | Commanization of resource | 1000 | 100 |
| 2 | Negotiation Savings | xx | Feb-22 | Negotiation on going with supplier | XX | XX |
E. Opportunity Management
1. Variation Orders: Additional activities requested by customers outside original scope offer opportunities to earn extra work and augment margins. Contract clauses defining calculation methodologies must be adhered to.
2. Options: Contracts with options allowing procurement increases at agreed prices. Exercising deadlines must be monitored and highlighted to customers proactively.
F. Working Capital Management
1. Billing & Collection: Invoices with supporting documents must be raised promptly upon achieving contract billing milestones.
2. Cash-Outs: Classified into:
- a. Capex: One-time expenditures for capability/capacity. Split into (i) Project Specific Capex (used exclusively, then scrapped/handed over), and (ii) Common Capex (used across projects).
- b. Operational: Revenue expenditures for day-to-day project activities (travel, salary, rent).
CPI = Current Cash Status – Planned Cash Status
Where: Cash Status = Cash Received – Cash Out. Positive CPI signifies a healthier cash position than budget; negative CPI warrants immediate root-cause remediation.
G. Contract Management: Essential Financial Clauses
H. Change in the Contract Schedule: Acceleration vs Delay
1. Acceleration: When customer requests completion prior to original schedule. Project Managers must deploy added resources, evaluate cost/quality impacts, negotiate compensation and revised quality metrics before proceeding.
2. Delay:
- a. Customer Delay: Late inputs or site access. Costs are fully claimable subject to contractual notice and detailed documentary proof.
- b. Contractor Delay: Execution/recruitment delays. Costs are unclaimable; customers may levy liquidated damages. Remedies: add resources, negotiate time extensions without cost claims, outsource work packages, or uncover savings in the savings register.
I. Sharing of Project Learnings (Post-Mortem Knowledge Transfer)
Examines deviations impacting time, cost, or quality. Document: (i) Root cause, (ii) Identification trigger, (iii) Mitigation applied.
Captures positive achievements exceeding plan. Document: (i) Improvement ideas, (ii) Identification & implementation method.
Conclusion
Project Management is a complex process, however, if done right, it can ensure that the objectives of projects are achieved. Above are some of the processes which must be deployed by the project managers to identify risks in the project and mitigate the same or find additional savings.